problem with Progress Bar

Post Reply
gilles6
Posts: 5
Joined: 28 Nov 21 22:45

problem with Progress Bar

Post by gilles6 »

Hi,
The progress bar of ingestWizard stays stuck on 33,3% systematically when I import photo folders in PS. Under the bar, there is the label 'Labels assignment'.
The import seems to be done correctly but without any visibility...so I have to wait hours to be sure!
I use PS version 6.6.0.4047 on Mac OS Big Sur.
Is this a known problem? How do I know if the import is working?
Hert
Posts: 7871
Joined: 13 Sep 03 6:24

Re: problem with Progress Bar

Post by Hert »

A warm welcome to the forum.
The 33% step is where the image references in the database to the files are created. Depending on how many files you are trying to import at once that will take longer to complete. Since this is a single database operation it is not possible to show progress for this step. PSU just has to wait for the database to complete and return the operation to the application. During the wait time, PSU should show a continuous progress indication: sweeping progress bar from left<->right).
As an alternative you can import smaller batches (sub folder)?
This is a user-to-user forum. If you have suggestions, requests or need support then please send a message
gilles6
Posts: 5
Joined: 28 Nov 21 22:45

Re: problem with Progress Bar

Post by gilles6 »

thank you Hert
Post Reply